The administration and maintenance of the roads of the Prešov self-governing region (SÚC PSK) begins these days with the reconstruction of bridge no. M4597 (3136-003), located in the urban area of the village of Vislanka (Stará Ľubovňa district).
The main construction works that SÚC PSK plans to carry out as part of this investment event include:
establishment of construction site equipment, laying out engineering networks and edges of excavations
demolition works
construction of a temporary structure serving to divert the flow of the stream
realization of an embankment for widening the crown of the road
drawing up a plan for a new road construction
implementation of a new road structure, including the laying of a new road cover
switchgear of the LV (low voltage) wiring harness
backfilling of roadsides
removal of the construction site
The assumption of completion of work on the given bridge object is April 2023.
The financing of the building, the total cost of which is more than €463,000, is provided by a loan provided by the European Investment Bank PSK.
During the implementation of the works, traffic restrictions in the form of a partial road closure will apply on the given section. The traffic, which will be led alternately in one lane in both directions, will be regulated by portable traffic signs using light signaling. Road users must also expect a reduced permitted speed of 30 km/h.